Wausa School construction; moving along

WAUSA — For the rest of the month of February, Boyd Jones is focused on finishing drywall and completing work to get mechanical, electrical, and plumbing systems installed above the ceilings. Boyd Jones expects painting to begin in early March.

Interior framing for walls is finished, which set crews up to begin installing drywall late in the week of Feb. 3. Finish crews will begin mudding joints and finishing drywall on the week of Feb. 17. After drywall is complete and crews finish work on MEP systems above the ceilings, painting can begin.